Here we go again! We must be mad
Second extension will give us a new kitchen diner space with separate utility room plus a fifth bedroom with en suite in space vacated by the old kitchen and dining room
Week 1 – Day 1 – 27 January 2014



Parts of the foundations from the old garage that used to be on the site show themselves.
Plus what looked like an air raid siren, some other rusting metal work and some ‘vintage’ bottles
The ground to the front of the extension was very crumbly so had to be shuttered before concrete pour…


Day 3 – 29 Jan Even so three trucks of concrete required to fill the foundations

Day 5 – 31 Jan – Foundations complete. Soak-away in and rain drains installed


Brickwork, Insulation and sand arrive

Week 2 – Brickwork to damp course mostly complete

Week 3 – 11-Feb – Main brickies arrive and it begins to rise. Weather causing kitchen area to look like a pool

Day 14 – 13-Feb – Window openings appear. The are higher that usual for kitchen cabinets to fit beneath

Day 14 – 13 Feb – Oops extra window installed to front……


Day 15 – 14 Feb……But soon remedied

Week 4 – 16 – 17 Feb – Beginning to be able to imagine what the bi-fold door will look like

Day 19 – 20 Feb Uprights for the steel work installed
Day 20 – 21 Feb Scaffolding erected
Week 5 24 – 28 Feb
Up to roof height – steel delivered for over back doors

It’s a big one

Steel Uprights ready for main steel roof supports


and toward the end of the week the steel in place



Week 6 – 3 – 7 Mar
Soldier bricks complete the work that the brickies need to do, for now at least
Week 7 – 10 – 14 Mar
Skip arrives!
Week 7 – 10 – 14 Mar
Vacating the dining room and moving table to the hallway in prep for the breakthrough

The calm before the storm

The chimney is stripped of marble. Nick brought his rubber hammer to make sure non was chipped

The roof is partially demolished in prep for the steelwork. The old beams are exposed ready for removal

Our new kitchen door way is nearly ready. All the wood is gone from the dining room

The walls get the message – They are on the way out

Uncle Moss’s M&M Crane on site to lift the beams




The beasts are in place

The old column is being stripped


Supports – looking a bit hairy…

Week 8
Foundations for the new wall between the new kitchen and from room

and the new wall in place plus RSJ

Week 9
No Progress – Issues with building control re roof construction
Week 10
No Progress
Week 11
Welding on the steels





Roof arrives

Week 12 – 23 April
Hurrah! First side on complete with velux framing

A day later and opposite side and rear pitch i place…looking good

Shaping up in side. Should be a nice space for entertaining


Middle window slightly longer which looks good

The side velux should get some much needed natural light in to the back of the kitchen


Couldn’t resist getting just one more velux added – just to balance things up



Soffits on


Can see the outline now and looking much more balanced that before


Roof battening


Nearly complete from the back

…and from the front

All the velux in now

a vast amount of first fit electrics to go in now
24 June
Scaffolding down Guttering up and first fit electrics almost complete



Looking forward to getting our house back and not having to eat in the hallway;-)

Rear door installed



Roof Insulation and bulkhead in for downlighters

Windows on order, so boarded for now

Plasterboard on


19 July 2014
Plaster work complete and Underfloor heating in

awaiting the windows


Screeding done


Our new ramshackle kitchen part painted with some of the lighting installed


Speakers installed


A view from the Lounge – from room squared off


when one door closes………


Daniels bedroom windows being installed – The archers slit is the side of the ensuite window
also kitchen door now moved to utility


Side windows in


New Corridor to Utility and Kitchen takes shape

Old kitchen – New Bedroom for Becky
New kitchen installed





